二滩水电站大坝基础固结灌浆由世界著名的专业商TREVI基础公司负责施工,采用国际通用的FIDIC模式管理,施工信息反馈快,监理工程师决策快,是固结灌浆顺利实施的关键。大坝基础固结灌浆的设计、施工是先进的,特别是有盖重引管灌浆的方法,成功地解决了大坝混凝土浇筑与基础固结灌浆相互干扰的问题。
The foundation consolidation grouting of Ertan Hydropower Station is under the construction of TREVI Foundation, a world-famous professional company. It adopts international FIDIC mode management, quick feedback of construction information and quick decision of supervision engineer. It is the key to the smooth implementation of consolidation grouting. The design and construction of the foundation consolidation grouting of the dam are advanced, especially the method of covered heavy-draft tube grouting, which successfully solved the mutual interference problem between the dam concrete pouring and the foundation consolidation grouting.