在水电站建設中,关於厂房修建部分实行土建与机电安装的平行交叉作業,对縮短水电站建設时間具有重要的意义。官廰水电站在这方面取得了一定的經驗。他們在各个大小环節上都实行了平行交叉作業,解决了相互干擾問題,加速了施工進度,縮短了工朝。因此这个經驗是值得我們各水电站建設工地学習和参考的。但这个經驗目前还不够十分完善,有待我們大家在今后工作中進一步丰富和充实。
During the construction of hydropower stations, the parallel cross-over operation between civil works and mechanical and electrical installation on the part of the building construction is of great significance to shorten the construction time of hydropower stations. Guanli Hydropower Station in this area has gained some experience. They conducted parallel cross-cutting exercises in all aspects of their dimensions, solved the mutual interference problem, accelerated the construction progress and shortened the workmanship. Therefore, this experience is worth learning and reference for construction site of our hydropower station. However, this experience is not yet perfect enough for us to further enrich and enrich our work in the future.